At Longs Peak Avenue, the construction is finished. Longmont completed its Federal Railroad Administration-approved safety work there in July 2026, along with three other crossings at 3rd, 9th and 17th avenues. Across the four crossings, the improvements vary by location and include upgraded gates, raised medians, fencing and enhanced pedestrian crossings. Trains still sound their horns at all four. Under the City's current schedule, they will keep doing so at Longs Peak Avenue until summer 2027.
That gap between finished concrete and actual quiet matters if you're touring homes near downtown Longmont this fall. The BNSF line carries up to 17 trains a day through town, and federal rules require a horn at every public crossing. On October 9, the City broke ground on the 1st & Main Transit Station a few blocks away. Over the next three years, homes along this corridor will get quieter and better connected. Each block gets there on its own date, and some of those dates are already moving.
Building a crossing doesn't make it quiet. The City's quiet zone page says horns stop routinely only after the Federal Railroad Administration formally designates each crossing as part of a quiet zone. Longmont has split its 17 crossings into seven potential quiet zones along a corridor that will eventually run from Hover Street to State Highway 66. A $4 million FRA grant covers 14 of those crossings. The City is funding the rest through its voter-approved ¾-cent Street Fund tax.
So a finished crossing can still wait on its neighbors. Three of the four crossings completed in July are scheduled to go quiet alongside crossings that only started construction this late summer.
The schedule has also shifted in just three months. In its July 10 release, the City expected 17th Avenue to go quiet in fall 2026 and the 5th Avenue and Terry Street closures in winter 2026. The City's page as of October 10 now lists all three for early 2027.
| Crossing | Construction window | Horns expected to stop, July 2026 estimate | Horns expected to stop, October 2026 estimate |
|---|---|---|---|
| 17th Ave | Done, July 2026 | Fall 2026 | Early 2027 |
| 5th Ave/Atwood, Terry St/1st Ave | Late summer 2026 to early 2027 | Winter 2026 | Early 2027 |
| 3rd, Longs Peak, 9th | Done, July 2026 | Summer 2027 | Summer 2027 |
| 4th, 6th, 21st | Late summer 2026 to early 2027 | Summer 2027 | Summer 2027 |
| Main St, Coffman St, Mountain View Ave | Spring to fall 2027 | Spring 2028 | Spring 2028 |
| State Highway 66, Hover St | Summer to winter 2027 | Summer 2028 | Summer 2028 |
The City's July list also puts Emery Street, which is already upgraded, in the spring 2028 group.
Two crossings are changing in a different way. Once construction is done, 5th Avenue at Atwood and 1st Avenue at Terry Street will close permanently to through traffic. Noraa Concrete Construction is building that second group now. On those blocks, the horns will stop, but you'll also lose that route across the tracks. That should factor into how you judge the commute from a house nearby.
The crossings closest to the heart of downtown are scheduled last, and the transit project explains why. City Manager Harold Dominguez said staff would coordinate the parking garage, the Coffman Street extension, railroad quiet zones, the Boston Avenue connections and the planned multifamily housing to reduce traffic and other disruptions. The City's proposed 2027–2031 capital plan puts the Coffman crossing's quiet zone improvements in the quiet zone project. Coffman pedestrian and bike work falls under the station-area project.
In practice, homes nearest 1st and Main face the longest stretch of construction and the latest horn relief. Under the current schedule, that relief arrives in spring 2028.
The project driving that sequence is big. The Times-Call reports the transit center and Coffman Street extension cost $70 million and are targeted for completion by the end of 2027. The five-story building will have 10 bus bays, about 700 parking spaces and bicycle storage. Funding includes $16.4 million from RTD, a $4 million state Transit-Oriented Communities grant, and more than $17.6 million the City has put into property and related costs. In September, City Council unanimously authorized up to $38 million in certificates of participation and approved the 29.5-acre 1st and Main Urban Renewal Plan.
If you're weighing a home near downtown, separate what you can use today from what is scheduled and what depends on a vote. The timeline looks like this:
"We're building this to make it easier for residents to get to school, get to work, and build careers here in Longmont." Harold Dominguez, Longmont city manager, quoted in BizWest
Three trains a day in each direction makes for a thin commuter schedule, and that is where the November ballot comes in. Ballot Issue 7A proposes a 0.333% sales and use tax for the Front Range Passenger Rail District and authorizes $580 million in district debt. The Colorado Sun explains that the tax applies inside the district's included municipalities and special districts, Longmont and Boulder among them. It doesn't cover every address in the counties where 7A appears on the ballot.
According to the district's published plan, the 2029 starter service goes ahead on existing funding either way. The tax-funded plan adds two Denver–Pueblo round trips by 2032 and later aims for up to 10 daily northern round trips. The vote doesn't decide whether a train stops in Longmont. It decides how often trains run later on.
Longmont's citywide sales data shows attached homes moving much more slowly than detached homes. According to the Longmont Association of REALTORS® August 2026 update, which uses Colorado Association of REALTORS® data:
These are citywide figures for a single month. The report itself warns that small samples can make one month look extreme, and its prices don't account for seller concessions. No September report for Longmont had been posted as of October 10.
Even with those limits, a market with 5.3 months of supply gives attached-home buyers more time to ask questions than a market with 2.8. If you're buying a townhome or condo near the tracks this fall, you're paying today's price for a block whose horns, bus service and construction traffic will all change on dates the City has already revised once.
Do the crossing gates finished in July mean horns have stopped there? No. Horns continue until the FRA designates each crossing as a quiet zone. The City currently expects 17th Avenue in early 2027 and 3rd, 9th and Longs Peak avenues in summer 2027.
Is there transit from downtown Longmont to the airport right now? Yes. Route AL has run hourly from 8th Avenue and Coffman Street to DIA since September 27, 2026.
Will Longmont get rail service if 7A fails? The district says the 2029 starter service of three daily round trips, with a Longmont stop, is funded by existing commitments. More frequent service depends on the new tax.
If you're comparing homes along Longmont's rail corridor, we'll check each address against the City's current quiet zone and construction schedule and pull the attached and detached comps that apply to that block. Reach out to Paul & Kam Real Estate and let's go through the crossing dates before you write an offer.